From idea to keys

What each type of project involves — stages, typical durations and the permits you will need.

Typical project

Months by phase

Stacked bars — the length of each phase in a typical project.

  • Design
  • Approvals
  • Construction
  • Handover
0122436486072
2.1 yrs
10.5 mo
14 mo
6 mo
5.3 yrs
7 mo
Building a new houseRenovating an old structureAdding a floor or extensionInterior redesignUrban renewalCommercial fit-out
Budget over time

When the money is spent

Cumulative share of the budget across each project's timeline. Hover a chart for details.

Building a new house2.1 yrs
100%50%0%
012.5 mo2.1 yrs
Renovating an old structure10.5 mo
100%50%0%
05.3 mo10.5 mo
Adding a floor or extension14 mo
100%50%0%
07 mo14 mo
Interior redesign6 mo
100%50%0%
03 mo6 mo
Urban renewal5.3 yrs
100%50%0%
02.6 yrs5.3 yrs
Commercial fit-out7 mo
100%50%0%
03.5 mo7 mo
In detail

Every procedure, step by step

  • Design
  • Approvals
  • Construction
  • Handover
Procedures with stages, durations and permits
01Building a new houseFrom an empty plot to moving in.
  1. 1.Plot & zoning check1 mo · 1%
  2. 2.Concept design3 mo · 3%
  3. 3.Permit process6 mo · 3%
  4. 4.Construction drawings & tenders2 mo · 3%
  5. 5.Construction & supervision12 mo · 87%
  6. 6.Handover & Form 41 mo · 3%
Duration1.5–2.5 yearstypically 2.1 yrsPermitsBuilding permit, utility connections, Form 4
02Renovating an old structureBringing an existing building back to life.
  1. 1.Structural survey1 mo · 2%
  2. 2.Design & strengthening plan2 mo · 5%
  3. 3.Permits (if needed)2 mo · 2%
  4. 4.Demolition & reinforcement2 mo · 20%
  5. 5.Systems & finishes3 mo · 68%
  6. 6.Handover0.5 mo · 3%
Duration6–14 monthstypically 10.5 moPermitsPermit if structure or facade change; engineer's survey
03Adding a floor or extensionMore space on the house you love.
  1. 1.Building rights check1 mo · 1%
  2. 2.Structural assessment1 mo · 2%
  3. 3.Design2 mo · 4%
  4. 4.Permit4 mo · 3%
  5. 5.Construction5 mo · 87%
  6. 6.Final inspection1 mo · 3%
Duration10–18 monthstypically 14 moPermitsBuilding permit, neighbours' notice, structural approval
04Interior redesignNew layout, materials and light — same walls.
  1. 1.Brief & measured survey0.5 mo · 2%
  2. 2.Layout & concept1 mo · 4%
  3. 3.Materials & details1 mo · 4%
  4. 4.Procurement1 mo · 40%
  5. 5.Execution2 mo · 47%
  6. 6.Styling0.5 mo · 3%
Duration3–8 monthstypically 6 moPermitsUsually none
05Urban renewal (TAMA 38 / Pinui-Binui)Strengthening or rebuilding a residential block.
  1. 1.Building survey2 mo · 1%
  2. 2.Residents' agreement12 mo · 1%
  3. 3.Developer selection4 mo · 1%
  4. 4.Planning & permits14 mo · 5%
  5. 5.Construction2.5 yrs · 90%
  6. 6.Residents return1 mo · 2%
Duration3–7 yearstypically 5.3 yrsPermitsResidents' majority, municipal approval, building permit
06Commercial fit-outOffices, shops and restaurants, ready to open.
  1. 1.Brief & site survey0.5 mo · 2%
  2. 2.Concept & layout1 mo · 4%
  3. 3.Licensing drawings1 mo · 3%
  4. 4.Tender & contractor1 mo · 2%
  5. 5.Build-out3 mo · 86%
  6. 6.Opening0.5 mo · 3%
Duration4–9 monthstypically 7 moPermitsBusiness licence, fire-safety approval

Durations are typical ranges for projects in Israel and depend on the site, the municipality and the scope of work.